Invoice #INV-8836 Overdue

Meridian Electric · Oak St Addition · received Jul 24, 2026

Overdue by 6 days — terms Net 30, due Jul 25 Unconditional lien waiver has not been received. Approving will queue payment but hold release until the waiver clears.
Vendor
Meridian Electric
Job
Oak St Addition
Purchase order
PO-1187
Terms
Net 30

Line items

5 lines · coded to 2 cost codes
DescriptionCost codeGL accountAmount
Rough-in electrical — 2nd floor addition26-05005100 · Subcontractor$3,200.00
Service upgrade — 200A panel26-05005100 · Subcontractor$1,850.00
Recessed lighting — 14 fixtures26-05005100 · Subcontractor$1,120.00
Exterior GFCI + landscape circuits CO-0326-09005100 · Subcontractor$680.00
Permit fee reimbursement01-41005400 · Permits$410.00
Subtotal$7,260.00
Sales tax$390.00
Retainage held (10%)−$765.00
Net payable$6,885.00

Approval history

Submitted by A. ReyesAP clerk · Jul 24, 9:12 AM
Approved by D. WhitfieldProject manager · Jul 26, 4:47 PM CO-03 circuits confirmed installed. Scope matches the walk-through.
Controller approvalAwaiting you · escalated Jul 29

Verification

1 hold
3-way matchPO-1187 ↔ receipt ↔ invoice
Change order CO-03Approved Jul 18 · $680
W-9 & insuranceCOI valid through Dec 2026
Lien waiverConditional received · unconditional pending

Budget · 26-0500 Electrical

$18,420 committedof $24,000
Remaining after approval$5,580

QuickBooks

Sync status Not synced
QBO class Oak St Addition
Vendor record Matched

A bill is created in QuickBooks on approval. Retainage posts to 2150 · Retainage payable.